Is there a way to set resource availability by task (not project) during a specific time period in MS Project 2013 ?
For example there is a resource allocated to Task 1 that starts in Dec 2015 and ends Jan 2017. The same resource will also work on Task 2 that starts Dec 2016 and ends Jan 2018. During the overlap period of Dec 2016 - Jan 2017 the resource is available to the project a 100%, however the availability for each task is only 50%. During the period where there is no overlap the resource is available a 100% to the respective task
Is there a way to define this type of resource availability to a task using a date range? I am aware of the alternative of manually applying contouring at a Day by Day level during that time frame however that will be very tedious if there are multiple resources with the same scenario.
Thanks!