I have a situation where we will be doing a conversion over a weekend in order to minimize impact to the company. Additionally, this task should be delayed until 3 weeks after a predecessor task. What are some ways to handle both of these together?
- I have indicated that this task should use the 24 hour calendar
- I have indicated that this task should ignore the resource calendar
- In doing so, I have had to indicate that the lag from the predecessor needs to be 2 months in order to get the date of the subsequent task pushed out 3 weeks.
Is there a way to keep from having to use the 2 month lag? The date ends up right, but my OCD starts twitching for having to indicate 2 months for a 3 week spread.