when I enter the start times and end times of tasks, software calculates duration of task in decimal form. I have checked calender setting and I think it is correct but I can't solve this problem. I don't know what should I do?

  • I'd check the default start and end times in File > Options. As an aside, you shouldn't be entering start and end dates or times of tasks - those should be calculated by Project - unless you are working solely with manually scheduled tasks. – JulieS Jan 25 '16 at 20:25
0

Durations are tracked by MS Project to the minute level. Using decimals in durations allows detail in durations for:

  • tasks starting or ending at times other than the work day start and finish that you define as defaults
  • tasks that take fractional amounts of a day, say 2.5 hours, at resource usage of 100%

Also, decimals allow easier aggregations of these for summarization.

| improve this answer | |

Your Answer

By clicking “Post Your Answer”, you agree to our terms of service, privacy policy and cookie policy

Not the answer you're looking for? Browse other questions tagged or ask your own question.