0

I am having a difficult time understanding how requirements are tracked through the project.

I have a list of requirements - do I link these to deliverables during planning?

Do i periodically review requirements, and if so, do i check off or document somewhere if and how it was fulfilled?

The requirements traceability matches a requirement to project objectives, but this seems more for alignment to goals than tracking progress.

Is there a particular document and process that provides for documenting the fulfillment of a requirement?

Thanks.

1 Answer 1

0

It is the project itself that links the requirements to the deliverables. All projects consist of a series of tasks for deploying the requirements in some way, and planning consists of planning and scheduling those tasks in time to determine the delivery timescales.

Whether or not the requirements are "allowed" to change, and the acceptable pace of change in a project requirements and scope, will differ from organisation to organisation and from project approach to approach. So it is not possible to answer whether you need to be reviewing requirements- but typically it would not be the Project Manager who has responsibility for reviewing requirements, it would be an ongoing process between the "business" (i.e the customer) and the various team members (i.e. business analysts, requirements analysts etc.) who usually translate customer requirements into deliverable goals and objectives. The Project Manager would facilitate the review process and have some oversight of the review and outcomes, as well as tracking its progress against the planned review tasks.

Requirements Traceability attempts to ensure that for every requirement or goal stated and defined in a project, there is a corresponding set of appropriate activities that deliver that requirement and test it has been delivered accurately. This is usually performed within various documents and allows someone to start with a documented requirement and trace that requirement through various documents (Requirements Spec, Functional Spec, Technical Design Spec, various development artefacts, Test Plans, Test Scripts, UAT Scripts and UAT Signoff etc. etc.). Then by ensuring all requirements are carried through all documents and have demonstrable deliverables, it can be easily demonstrated that a project delivers on its goals and requirements.

1
  • Thanks. When a customer accepts the deliverables, they then accept the requirements as met.
    – Tyler
    Mar 18, 2016 at 19:46

Your Answer

By clicking “Post Your Answer”, you agree to our terms of service and acknowledge you have read our privacy policy.

Not the answer you're looking for? Browse other questions tagged or ask your own question.