I have a project where I am setting resources at 60% availability in general. However, for certain tasks, I would like to divide the work proportionally between two resources. The best way I can describe it is with an example.
Say I have a 100 hour task. I have it set to Fixed Work. I have two resources, Tim and Bob, each set at 60% availability. Tim is only responsible for 10% of the work for this task, leaving Bob 90% of the task.
I can manually assign 10 hours to Tim and 90 hours to Bob using the Task Usage view, but for a schedule with several hundred lines, this can get tedious. Is there a way to select multiple tasks and ration them out like I want?