for example, if I have two tasks start at different dates that end at the same date.
My problem is, if I try to link these two tasks, the dates will automatically change, not the original dates I want to keep.
Is there a way to solve this? Thanks!
Project Management Stack Exchange is a question and answer site for project managers. It only takes a minute to sign up.
Sign up to join this communityfor example, if I have two tasks start at different dates that end at the same date.
My problem is, if I try to link these two tasks, the dates will automatically change, not the original dates I want to keep.
Is there a way to solve this? Thanks!
Link the tasks as Finish-to-Finish instead of the default Finish-to-Start. Change the Predecessor field to say 2FF.