0

for example, if I have two tasks start at different dates that end at the same date.

enter image description here

My problem is, if I try to link these two tasks, the dates will automatically change, not the original dates I want to keep.

enter image description here

Is there a way to solve this? Thanks!

2

Link the tasks as Finish-to-Finish instead of the default Finish-to-Start. Change the Predecessor field to say 2FF.

Your Answer

By clicking “Post Your Answer”, you agree to our terms of service, privacy policy and cookie policy

Not the answer you're looking for? Browse other questions tagged or ask your own question.