for example, if I have two tasks start at different dates that end at the same date.

enter image description here

My problem is, if I try to link these two tasks, the dates will automatically change, not the original dates I want to keep.

enter image description here

Is there a way to solve this? Thanks!

1 Answer 1

2

Link the tasks as Finish-to-Finish instead of the default Finish-to-Start. Change the Predecessor field to say 2FF.