0

When a task is late in the status how can we set it up to show how many days it's late not just late? I want to see on each task how many days it's late.

1 Answer 1

3

Firstly you need to Baseline your plan at the start of the project, when all the planning has been done and you have a plan you are happy with.

Then add the Column 'Finish Variance' to your view.

Whenever the currently forecast Finish date is different to the date it was supposed to have been in the original forecase (i.e. the baselined plan), the difference will be shown in the Finish Variance column.

11
  • this is what i did and still sowing 0 it should show the diff from 4/11 to today
    – Abea name
    May 10, 2016 at 17:51
  • Late 0% 0 days 4/11/16 4/11/16 Late 0% 0 days 4/11/16 4/11/16 Late 0% 0 days 4/11/16 8/26/16
    – Abea name
    May 10, 2016 at 17:51
  • You cannot have baselined at the start correctly. Remember, there is no point baselining now that the variance has occurred. It absolutely does work, I double checked everything I said before posting my answer
    – Marv Mills
    May 10, 2016 at 17:53
  • meaning to say that there is no way to test it ?
    – Abea name
    May 10, 2016 at 18:00
  • can u advise any online help or youtube to explore this ?
    – Abea name
    May 10, 2016 at 18:07

Your Answer

By clicking “Post Your Answer”, you agree to our terms of service and acknowledge that you have read and understand our privacy policy and code of conduct.

Not the answer you're looking for? Browse other questions tagged or ask your own question.