0

We all know that in Prince2, If a project is no longer justified it should be stopped. That is, The justification for the project should remain valid. However, can the Continued Busines Justification for a project change in Prince2? or must it remain the same throughout the project ?

2

Of course the business reasons to do a project might change. It might become more interesting to do a project, or less... It all depends on the environment you're in:

  • the strategy of the department or larger organization might change, e.g. it's no longer our core business; or new responsibilities make the need for the new system even more important.
  • there is a change in legislation that forces us to do more; or makes the desired benefits less likely...
  • the competition has launched a similar product or service, and is now claiming a part of the market you were hoping for.

It's inherent to a project that it involves change, so also the business rational might change. As long as there still is a business justification, it's fine. PRINCE2 does not state it should be fixed! But rather it should be reviewed regularly, and verified if it still makes sense to do/continue the project.

Your Answer

By clicking “Post Your Answer”, you agree to our terms of service, privacy policy and cookie policy

Not the answer you're looking for? Browse other questions tagged or ask your own question.