I'm trying to make a portion of my MS Project schedule work backwards, and it's not working quite right. I'm hoping you can help.
I have a schedule where Task 45 ends on 2/1/17. Tasks 46 through 50 are all chained together, Finish-to-Start. I want Task 50 to end on the same day as Task 45 (2/1/17) and for Tasks 46-49 to all start as late as possible but still be done in time to have Task 50 end on the same day as Task 45.
To do this, I've set up Tasks 46-49 to start as late as possible, and for Task 50 to start as early as possible with Tasks 45FF and 49FS as predecessors.
Unfortunately what is happening is that Task 50 is ending on the project's end date, not on the same day as Task 45. It appears that Project is looking at the predecessors for Task 50 and thinking that as long as it ends some time after Task 45 it's ok. What I want it to tell Project that Tasks 45 and 50 must end on the same day. Is there a way to do that without entering in a specific date?