0

I am involved in a project for my summer internship. Prior to the start of the internship, I have set several milestones to help me track the progress made toward reaching the goals of the project.

After few weeks; unfortunately, I have noticed that the project tasks that I was working on are not exactly part of the ordered milestone that I was planning to achieve. This might be because I did not have a detailed understanding of the project and the specific methods to reach the project goal.

My question is what should I consider at this point so I can keep track with the project time limit. What is the practical practice to consider to complete the project with minimal losses?

1

"It is all relative to the project size" is the first sort of unspoken thing to understand-whether a 1-day, 1-month, or 1-year project. But, one basic way, no matter which tool or process you are using, is to force rank every task that needs to be completed under a milestone. If there are sub-tasks, then force rank them too under their respective tasks. Force ranking just means you assign a linear priority to each task that says, do this task 1st, do this other task 2nd, etc. and with estimated time to complete, and no task can have an equal assignment to another(so there is no ambiguity), until you get through all the tasks for that day/milestone. Of course this is all relative. And adding in dependencies other things the team is doing is another level. But for a single person, you'll need to have broken down your tasks into a relative number that can be accomplished in a day or two--otherwise your planning is still too high level. Again, also depends on your process. If you are using Agile, you might not detail too far out or you might change in the middle and reorganize, but that's ok too--because that's the process. It takes a little time to get the hang of force ranking, but the process of force ranking itself is very informative and you'll learn from it. Best part is, the learning is all relative to the project scope so it can be applied/leverage for future similar projects. Hope that helps.

Your Answer

By clicking “Post Your Answer”, you agree to our terms of service, privacy policy and cookie policy

Not the answer you're looking for? Browse other questions tagged or ask your own question.