1

I have organized my plan with Summary Tasks and many, many subtasks. Since it is a little bit difficult to manage every single subtask, I would like to do these operations:

  • assign predecessors to Summary Task
  • an effort estimation in terms of day (column Work) for every subtask
  • assign a resource for every subtask

And in this way have the subtasks automatically schedule with all dates.

As you can see from the image below I have assigned predecessors to summary tasks. The last column is the "Work" Column. The problem is that all the tasks start from 13/10/2016 and so the plan is not correct...

Do you know if there is some option in Project to have a tidy plan?

example

1
  • You need to Level the plan, which sorts out the over-allocation on each resource, which means that the tasks will be scheduled to start when there is resource free to do it.
    – Marv Mills
    Aug 9, 2016 at 14:37

1 Answer 1

2

Load your predecessor successor logic on your sub tasks. This will fix the problem.

That said, my practice is to load all the logic on the lowest level task I have in my schedule. I do not load any logic, predecessor-successor, resources, etc., in the hammock tasks.