I have organized my plan with Summary Tasks and many, many subtasks. Since it is a little bit difficult to manage every single subtask, I would like to do these operations:
- assign predecessors to Summary Task
- an effort estimation in terms of day (column Work) for every subtask
- assign a resource for every subtask
And in this way have the subtasks automatically schedule with all dates.
As you can see from the image below I have assigned predecessors to summary tasks. The last column is the "Work" Column. The problem is that all the tasks start from 13/10/2016 and so the plan is not correct...
Do you know if there is some option in Project to have a tidy plan?