1

Can I add columns in MS Project Pro to display time-phased costs? I would like to see a cost column for each year of the project. The year-column would only include costs for that year. I can almost do it by using formulas in custom-cost columns, but the tasks split between years are missed.

enter image description here

3
  • Are you talking about a particular tool? Or an approach? Aug 9, 2016 at 20:53
  • In a tool, I would like to see the columns in MS Project Pro project schedule Aug 10, 2016 at 19:20
  • It is worth mentioning MS Project in your post and including it as a tag as you will get more responses. I'm going to edit your post and add the MS Project tag now. Aug 10, 2016 at 19:31

1 Answer 1

1

Cost is timephased in either the Task Usage or Resource usage view (right hand side). Add Cost (right click in the background of the right hand side and choose Cost from the shortcut menu). Zoom out as needed.

Your Answer

By clicking “Post Your Answer”, you agree to our terms of service and acknowledge that you have read and understand our privacy policy and code of conduct.

Not the answer you're looking for? Browse other questions tagged or ask your own question.