I am trying to carry out following and having difficulty but I cannot figure out why, I am not expert at MS Project.
- I have one "100% completed" task with duration 35days
- No Resources have been assigned to this
- I have set the task type to "Fixed Work"
- I want to add a "work" of 111 hours to this
- When I type in 111 hours in work column it changes duration to 13.88days (calculated by 8hrs/d)
- When I extend the duration back from 13.88days to 35days, it changes the "work" to 280hrs (35d x 8hrs/d)
Why does it do this? I thought "Fixed Work" tasks don't change "work"...
thank you.