3

I am a relatively new scheduler to my company and new to project scheduling and earned value. My company has training sessions but some things remain unclear and the answers I am getting from some folks here do not make a lot of sense.

I am told there are several ways of claiming % complete and that each way has issues with them in terms of subjectivity or accuracy. I was told that physical % complete is the most accurate since it's something you can count. However, it does not make sense in terms of how planned value (PV or BCWS) is calculated and how I would take EV.

Here is the issue: I have three team members working a project that is supposed to last 20 days. 20 is my duration. This project will cost (BAC) $6,400. So my cumulative budget (S curve) across those 20 days is pretty much a straight line going up. So PV at day 10 will be $3,200.

Physically, the work is what they call back loaded so by day 10, they will only be 30% physically complete, so EV will only equal $1,920. This would mean that we are behind schedule when we really are not behind. Also, assuming costs are what they are supposed to be, AC would be, $3,200 and then this would mean we are also overrunning costs which would also not be accurate.

I am confused as to how physical complete is desired but then this scenario would make everything not accurate.

Help!!!

1
  • What is the question?
    – MCW
    Dec 26, 2016 at 20:29

1 Answer 1

1

I would map your physical % complete with the PV/BAC for any given period, and then when you complete a specific physical % of the work, you can claim the mapped PV/BAC as your earnings.

enter image description here

This is a graph that shows the S-curves for PV/BAC, the top line; % work, the second top line; % complete, the third line; and physical %, the bottom line. The physical % lags as was your example.

So let's say we are in period 4 and you completed the work on time, you would be about 45% physical complete, which maps to 86% PV/BAC complete (draw a vertical line from the bottom curve all the way to the top line curve and then a horizontal line to the y axis.) Therefore, for 45% physical complete, you would claim 86% EV or BCWP.

Your Answer

By clicking “Post Your Answer”, you agree to our terms of service and acknowledge you have read our privacy policy.

Not the answer you're looking for? Browse other questions tagged or ask your own question.