been thinking about how to do this, maybe it requires a macro?

Scenario:

Resource A is allocated to Task 1 @ 50%, and Task 2 @ 50% for the same week. I now want to change the Task A allocation to 80%, which updates Work to 32hours, and want Task 2 to auto-update to 20% (and the respective Work to 8). Is this doable? Using leveling doesn't reallocate percentage but instead lengthens tasks.

Also appreciate that a particular difficulty is if Resource A is allocated to more than 2 tasks e.g. Task 1 @ 30%, Task 2 @ 30% and Task 3 @ 40%: if I update one, how does it take percent allocation from the other two?

0

There is no built-in method for Project to automatically change assignment units. The overallocation alert is there to tell you when a resource is overallocated, but it is up to the project manager/scheduler to decide how to resolve the overallocation.

Your Answer

By clicking “Post Your Answer”, you agree to our terms of service, privacy policy and cookie policy

Not the answer you're looking for? Browse other questions tagged or ask your own question.