So I have 9 projects that are working concurrently. Many of the resources used are the same. We have different work-plans for each, but we want to put it into one master-plan. I have created the master plan, but I need a calendar that shows all of the tasks and work-plans for all of the projects in one calendar. How do I do that?

  • 2
    Not an answer but "many of the resources used are the same" signals that there's quite a tricky time/priority management issue at your company/division. – Gürkan Çetin Feb 4 '17 at 18:37
1

You can create a master project by inserting the project plans together. I am guessing you have not created a resource pool file nor are you working on Project server. If the same resources work on the nine project plans, best to create a resource pool file and attach the resources to each plan.
see: https://support.office.com/en-us/article/Create-and-share-a-resource-pool-64a2416e-b811-4ddf-b039-e0347e233581

Your Answer

By clicking “Post Your Answer”, you agree to our terms of service, privacy policy and cookie policy

Not the answer you're looking for? Browse other questions tagged or ask your own question.