0

We want to make our Task ID's in microsoft project 1.1,1.2,1.3,1.4 and so on so it is clear which general task they fall under. At the moment they are displayed as 1,2,3,4,5.

Please help, thank you

  • I think you just need to indent (change outline level) on the tasks you want to be subordinate. Perhaps I don't fully understand your question? – Mark C. Wallace Dec 7 '16 at 18:28
1

One way to achieve this is to display the Work Breakdown Structure (WBS) as a column on the sheet.

By default, this will number the tasks as per your request: enter image description here

If this meets your requirement it is very easy to do. Right-click in the top bar of the sheet, at the position where you want the column, and select "Insert Column". Choose the column "WBS" and you have the result you want. Note that the original row / task numbers will still be present in the left margin, but one way round that is to drag that column's margin so that it has zero width.

Your Answer

By clicking “Post Your Answer”, you agree to our terms of service, privacy policy and cookie policy

Not the answer you're looking for? Browse other questions tagged or ask your own question.