0

I have multiple projects and each project has at least 2 stages. Some of the project stages can start in parallel while others start after one stage of the project ended. More, some projects depend on stages of other projects. Beside that, I have some processes that affect some of the projects and some stages of the projects are part of a common event. Now, how can I organize all this information efficiently to show both project stages and dependencies between projects?

3

You need to build an integrated master schedule. You need to pull in all your separate projects' schedules into one schedule and link them. You can link the work packages from different projects directly or you can create major and minor milestones within a sub project and link those, or a combination.

Based on Mark's comments below, I do need to add as part of my answer here that building and maintaining an IMS is not for the faint of heart. It requires capability and resource commitment and you need to have someone who knows what they're doing run it for you. A large IMS can become very complex quickly and subject to error. When that error surfaces, you will lose stakeholder confidence in the tool and that is very hard to get back. Not only this, but even when correct, your team members will accuse it of being incorrect when it begins to exhibit bad news. This is a lot of work but necessary work.

3
  • 1
    Integrated Master Schedule is not trivial; I've done it, but maintenance requires real effort. Don't do it idly; plan for it, and make a couple of tests before you show it off to management. Among other things, it is difficult to maintain consistent task numbering.
    – MCW
    Dec 8 '16 at 17:30
  • 1
    Huge P.I.T.A. Expensive to operate on a large program. Dec 8 '16 at 17:56
  • 1
    Your answer is correct and the best response - but I think it is important to note the PITA factor. OP should be prepared and should plan some time for maintenance of an integrated master schedule.
    – MCW
    Dec 8 '16 at 18:03

Your Answer

By clicking “Post Your Answer”, you agree to our terms of service, privacy policy and cookie policy

Not the answer you're looking for? Browse other questions tagged or ask your own question.