I'm in a group project at school. We built a MS Project file for our group, and set durations for all tasks. Everything is Auto-Scheduled. We also set up resources for ourselves to work on the tasks. For instance we have WBS task #1.1.1. This task has a duration of 7 days and has 10 hours of resources assigned to it. We then baselined the project file.
How do we enter the actual resources that were spent on that WBS item? Every time I enter something, it changes the duration or completion date. I just want the project file to know that we worked overtime on it (or under time). So that we can compare that to the baseline and keep a log of everything.