I'm working on project management with the client-side manager. We manage the cost with cost type ressources as we only know how much we are going to pay for each task and not how many hours of work and how much material are put into it.
My question is, when I use this type of ressources, why does MS Project not calculate EV, PV, etc. ? why does it only show EAC and BAC ?
Microsoft Project don't automatically calculate the EV and other variables: