-1

As a new Project Manager what techniques and tactics exist to ensure the requirements of the project are as clear as possible and consensus is achieved about the delivery outcome.

In this context I am referring to a sponsor or the most senior stakeholder available.

8
  • I'm voting to close this question as off-topic because homework question Feb 23, 2017 at 12:10
  • Hi Matthias, although I am really willing to help you, PM.SE is not the place for homework questions. Feb 23, 2017 at 12:11
  • My apologies, first time user. I was seeking the assistance of a friend who directed me here. Due to my time constraints I quickly published my questions without taking it into consideration.
    – matthias
    Feb 23, 2017 at 12:59
  • No worries - that's OK. I would suggest raising another question with a concrete case study. For instance "My team do not display full understanding of the project; what methods exist to ensure the team understands the project scope and also buys into the value of the delivery?" I will edit this question to make it more suitable about customer requirements. Feb 23, 2017 at 13:02
  • @venture2099 as you can tell I'm a novice, would you still be willing to give me some insight? The power point slides the course has provided beat around the bush quite a bit
    – matthias
    Feb 23, 2017 at 13:02

1 Answer 1

1

According to the PMBOK Standard, requirements are part of Scope Management.

"requirements .. as clear as possible and consensus is achieved about the delivery outcome." is the activity of Requirements elicitation, which is

"Elicitation is the activity of drawing out information from stakeholders and other sources to further understand the needs of the business, in order to address a problem or opportunity and identify the stakholders' preferences and conditions for the solution that will address those needs." (Requirements Management by PMI)

To achieve clarity, a range of activities should be performed. To write 'excellent requirement', Chapter 11 of [1] suggest to check if requirements are

  • Complete
  • Correct
  • Feasible
  • Necessary
  • Prioritized
  • Unambiguous!
  • Verifiable!

You should apply a clean writing approach, e.g. [precondition][trigger]software shall[response].

Additionally, consult IETF's RFC 2119, which contains information on requirements key words.

All this can lead you to the modelling of use cases, requirements, etc. see UML etc.

References:

Software Requirements by Wiegers & Beatty

Not the answer you're looking for? Browse other questions tagged or ask your own question.