I am going to build a project with several tasks and subtasks that have the same structure. For example:
- SECTION A
- task 1
- task 2
- task 3
- SECTION B
- task 1
- task 2
- task 3
- .......
What I would like to do is to place a formula in the "predecessor" field that would be something like "([actualID-1]FS+5days)" so that if I copy this formula on task 2 and task 3 line they will always refer to task 1 and task 2. In this way I can have hundreds of sections but only one formula to create the dependencies from the predecessors.
Is it a thing that can be done maybe with some custom field/column? Thanks