0

I have two tasks in ms project:

Task A, start: today 03/22/2017
Task B, predecessor: Task A FS+12eMonths
Task A and B are both 0 days long and automatically planned.
Task B start/finish is calculated: Saturday, 03/17/2018

Question 1: Why?
Question 2: What field or project settings would I have to use to achieve the date which I would expect (03/22/2018), without setting it to a manual field?

Regards

1 Answer 1

2

Microsoft seems to have hard-coded 1 emo = 30 edays. There is no setting to achieve your expected date, which is based on the variable human interpretation of "month." For workarounds, I would definitely stay away from task mode (i.e. "Manually-scheduled"). You could play with task calendars and/or constraints to force the second task to the date you expect. In the long run, users of CPM scheduling tools like MSP need to give up on such expectations altogether.

2
  • Thanks for explaining. How would you add a bunch of tasks which definitely take 10 months or 15 months? You won't calculate them on your own or would you?
    – Peter
    Mar 22, 2017 at 16:41
  • I would simply stay away from using months as a unit of time measurement in a project schedule. Work time is paramount, and calendar months do not have a consistent amount of working time. Use weeks or days.
    – Tom Boyle
    Mar 23, 2017 at 0:45

Your Answer

By clicking “Post Your Answer”, you agree to our terms of service and acknowledge that you have read and understand our privacy policy and code of conduct.

Not the answer you're looking for? Browse other questions tagged or ask your own question.