For Network Diagram, MS Project has the following fields in date format:
- Early Start
ES
. - Early Finish
EF
. - Late Start
LS
. - Late Finish
LF
Although, How can I display them in Network Diagram in numbers?
Project Management Stack Exchange is a question and answer site for project managers. It only takes a minute to sign up.
Sign up to join this communityFirst, from the Gantt Chart view you need to add 4 custom columns for (ES, EF, LS, LF).
Through clicking on Add New Column
from the table in right pane and choose columns of type numbers.
Custom Fields
.ProjDateDiff([Project Start],[Early Start])/[Minutes Per Day]
ProjDateDiff([Project Start],[Early Finish])/[Minutes Per Day]
ProjDateDiff([Project Start],[Late Start])/[Minutes Per Day]
(ProjDateDiff([Late Finish],[Project Start])/[Minutes Per Day])*-1
FORMAT
Tab click Boxes Styles
> More Templates > Create new Template.