I have a project structured with the below tasks:
Summary task A: Project Initiation
- Sub task A1
- Sub task A2
Summary task B: Project Design
- Sub task B1 (Workstream 1)
- Sub task B2 (Workstream 1)
- Sub task B3 (Workstream 2)
- Sub task B4 (Workstream 2)
Summary task C: Project Build
- Sub task C1 (Workstream 1)
- Sub task C2 (Workstream 1)
I need to report completion percentage of Workstream 1 and Workstream 2 separately.
The easiest way to do this would be to structure the project plan by workstream instead of project phases (Initiate, Design etc) but I don't have that option. I tried putting summary tasks under B, for example
Summary task B: Project Design
Sub summary task 1 (Workstream 1)
- Sub sub task B1 (WS1)
- Sub sub task B2 (Ws1)
etc.
But this didn't work for me as this only gives me workstream 1 completion within summary B. I need the completion for workstreams overall.
Would appreciate if the community could help me with this, or point me in the right direction. Thanks in advance!