0

I have a project structured with the below tasks:

Summary task A: Project Initiation

  • Sub task A1
  • Sub task A2

Summary task B: Project Design

  • Sub task B1 (Workstream 1)
  • Sub task B2 (Workstream 1)
  • Sub task B3 (Workstream 2)
  • Sub task B4 (Workstream 2)

Summary task C: Project Build

  • Sub task C1 (Workstream 1)
  • Sub task C2 (Workstream 1)

I need to report completion percentage of Workstream 1 and Workstream 2 separately.

The easiest way to do this would be to structure the project plan by workstream instead of project phases (Initiate, Design etc) but I don't have that option. I tried putting summary tasks under B, for example

Summary task B: Project Design

  • Sub summary task 1 (Workstream 1)

    • Sub sub task B1 (WS1)
    • Sub sub task B2 (Ws1)

etc.

But this didn't work for me as this only gives me workstream 1 completion within summary B. I need the completion for workstreams overall.

Would appreciate if the community could help me with this, or point me in the right direction. Thanks in advance!

0
  1. Make a custom field for Workstream, then assign your detailed tasks (NOT SUMMARY TASKS) the corresponding field values.
  2. On the Data group of the View Ribbon, create a new "Group by:" specification with the top level set to Group By your Workstream custom field.
  3. Implement the new GroupBy specification on any view with a table that shows %Complete. The GroupBy %Complete will be computed the same as a summary task %Complete (i.e. the duration-weighted average %Complete of the underlying tasks).

This is a very simple example. Combining Group-By specifications with hierarchical outline codes allows one to view any project from many different perspectives.

1
  • This is fantastic, Tom. This worked for me and I see this can be put to use in a lot of different ways. Thanks a lot!
    – xcentaur
    Apr 4 '17 at 4:56

Your Answer

By clicking “Post Your Answer”, you agree to our terms of service, privacy policy and cookie policy

Not the answer you're looking for? Browse other questions tagged or ask your own question.