I'm working on a schedule for teams that work Thurs-Thurs. I have a base calendar for the project that has the correct working days and times and have resource calendars for the individual teams.

Team TS2 is supposed to work 5/26, which is normally an off day. I added that as an exception in the resource calendar: enter image description here

When I go back to the Gantt chart it shows that task skipping 5/26, 5/27-5/31 (which it's supposed to, those are non-work days), and the vacation days seen in the picture above from 6/1-6/3, and has the final day fall on 6/4. If I try to put a constraint on the finish date for 5/26 it adds it to the project calendar, not the TS2 resource calendar. enter image description here

Exceptions default to non-working. Click on the Details... button and change it to working.enter image description here

  • I'm sorry, I should have been more clear. It is set to working and still the day is skipped. Here's another screenshot imgur.com/a/VOVVQ – Philip Robey Aug 14 '17 at 11:41

I figured it out. I assigned the base calendar to each task and I guess that was somehow overriding the resource calendar. Once I removed that everything was fine.

Your Answer

By clicking "Post Your Answer", you acknowledge that you have read our updated terms of service, privacy policy and cookie policy, and that your continued use of the website is subject to these policies.

Not the answer you're looking for? Browse other questions tagged or ask your own question.