0

I need to create a new resource that include a pay per day and quantity parameters.

For example, I have a resource "Rented Car - Type 1" with 60€/Day as daily cost.

In my project, I have a task (10 Days long) that requires 5 rented cars. I need MS project to tell me that the total cost of this task is 10*5*60=3000€.

When the task duration changes, the cost will change automatically.

1
  1. Project Calendar is Standard (5d x 8h)
  2. Fixed-units task w/ no task calendar.
  3. RentalCar Work Resource w/ Std. and OT rates of 60 EUR/day. (Since this is a rental car, the resource calendar should be 7d x 8h.)
  4. Assign RentalCar to task at 500%.
  5. Assign Drivers (resource r1) to task at 500% (these guys work 5 days/wk).
  6. Note because a 7dx8h resource is assigned, the task adopts the 7dx8h calendar. Rental car cost @ 10d duration is 3,000 EUR. Rental car cost @ 15d duration is 4,500 EUR.
| improve this answer | |

Your Answer

By clicking “Post Your Answer”, you agree to our terms of service, privacy policy and cookie policy

Not the answer you're looking for? Browse other questions tagged or ask your own question.