I would like to know what is the best way to handle cost adjustment to the baseline in MS project. Do you save the baseline when you adjust the cost when you get new estimate or not?

up vote 1 down vote accepted

You should save the baseline when you have an approved plan (that includes schedule, resources and costs). So if a change request is approved you should save the corresponding plan to the baseline.

If you have a new estimate that is not an approved budget Change request, you should track this as a forecast values, in the Cost fields, not in Baseline Cost.

  • @Igaleazzi than you. That's exactly the issue. It's not based on the approved plan. How do I track it through cost? Is thee a reference or an article I can follow? – jax Oct 19 '17 at 14:27
  • Have you already planned costs in your Project, and are you asking how to update it? Or are you asking how to plan costs to start with? – lgaleazzi Oct 19 '17 at 14:34
  • Yes the cost is already there and the project is 10% complete but now I have estimates that is different from the baseline cost. – jax Oct 19 '17 at 14:37
  • Alright. I assume you already saved the baseline in the past, in which case your baseline cost is safe and will remain unchanged. If you entered your costs in the "Fixed Costs" Task field, just enter the new value in that column. If you have used resources to calculate costs it is slightly more complicated. – lgaleazzi Oct 19 '17 at 14:41
  • You might have planned resources with a hourly cost. In this case you will Need to change the amount of work planned, and the cost will be calculated with the new amount of work. Adjusting the hourly rate is also possible in the resource details. – lgaleazzi Oct 19 '17 at 14:44

Your Answer

 

By clicking "Post Your Answer", you acknowledge that you have read our updated terms of service, privacy policy and cookie policy, and that your continued use of the website is subject to these policies.

Not the answer you're looking for? Browse other questions tagged or ask your own question.