0

enter image description here

This is my first ms-project. I want to plan the production and external operations of our plant. Production of reference #1 is something that will likely happen every 4 to 6 weeks (every time I receive a purchasing order). Is there any way I can group and save all these tasks together?

What I want is, instead of creating all tasks everytime I receive a PO, to select something like "Production of reference #1" and have all the tasks automatically created, and I will only need to decide when first task starts.

Is that possible?

2
  • @Tob , you've answered the question. Why not make it an answer ? Oct 22, 2017 at 11:27
  • @GürkanÇetin done :)
    – Tob
    Oct 22, 2017 at 12:21

1 Answer 1

0

You can group tasks by clicking on summary task under a headline task as @самиJ.D. pointed out. The corresponding option should be at the task menu. It might be possible to copy & paste the headline task (incl. the subtasks) and set a start date / relationship for the headline task.

3
  • 1
    The trick is to link only the main task, for copy-paste to work effectively. The subtasks can be inter-linked. Oct 22, 2017 at 12:24
  • So, what I have to do is to select a group of tasks and click on "summary task" so one global task is created, which includes all the other subtasks. In order to copy-paste that, I need to copy-paste the main global task. What I don't understand now, after checking it, is what's the differene between summary and indenting the tasks. Thank you for your answers! Oct 22, 2017 at 16:53
  • @самиJ.D. Sorry, translated it from my language, seems like MS picked a better word in yours.
    – Tob
    Oct 22, 2017 at 17:03

Your Answer

By clicking “Post Your Answer”, you agree to our terms of service and acknowledge you have read our privacy policy.

Not the answer you're looking for? Browse other questions tagged or ask your own question.