I'd like to use MS Project to analyse aircraft maintenance work force requirements for the next 18-24 months. The maintenance is a combination of repetitive and one-off servicings. I have task requirements for each servicing in Access, along with dependencies. Planners manage which servicings are performed during which maintenance events.
Given a high level schedule for maintenance events, I'd like to import the servicings and sub-tasks attached to each maintenance event, including task dependencies. Conceptually I can see where most of the data goes, and that I will have to be careful with task identification, but what I can't see is where the task dependency type (SF/FS/FF/SS) and lag are in the import/export maps? Is it possible to import these parameters?