0

Assumptions before reschedule:

  • Task 1 Finish Date: 1/30/2011
  • Task 2 depends on Task 1 by Finish-to-Start constraint (without any leads/lags) and thus start on 1/31/2011

After reschedule, Microsoft Project did this:

  • Task 1 Finish Date: 2/15/2011
  • Task 2 Start Date: 2/15/2011

As you see, MSP starts Task 2 exactly from day Task 1 is finished (2/15/2011). This is while, I suppose that Task 2 starts after Task 1 is finished (2/16/2011) due to the FS constraint. Can someone explain why MSP 2013 didn't start Task 2 on 2/16/2011?

  • 1
    Go to settings and select a date-time format that includes the time of day. You'll find Task 1 doesn't finish at the end of the day. Trace back until you find your error. – Tom Boyle Nov 14 '17 at 5:24
  • true, now how can I make MSP start Task 2 from new day (day after finishing day of Task 1) ? – DavidDe Nov 14 '17 at 5:52
  • You could always just type in the day you want at the Start of Task 2, but I suspect you want to do it right. What are the durations and start and finish dates (including time of day) of Task 1 and Task 2? – Tom Boyle Nov 14 '17 at 18:55

Your Answer

By clicking "Post Your Answer", you acknowledge that you have read our updated terms of service, privacy policy and cookie policy, and that your continued use of the website is subject to these policies.

Browse other questions tagged or ask your own question.