0

I want to assign a resource -Excavator- to a task -Task#1 : duration = 4 month- : 2 units in first 2 months and 5 units in second 2 months.

0

There are two ways of doing it. But first, make sure Excavator is a work resource (not a material resource) and its max. availability is 500% (to represent five available units).

First way (easy one):

  • Add two 2-month subtasks to Task 1: Task 2 and Task 3. Make Task 2 the predecessor of Task 3.
  • Assign Excavator to Task 2 at 200%.
  • Assign Excavator to Task 3 at 500%.

Second way (a little harder). Use this if you want to have only one task:

  • Assign Excavator to Task 1.
  • Use an assignment view (either "Task Usage" or "Resource Usage").
  • In the right pane, modify daily work from 8 hours to 16 hours. Do this for the first two months (yes, it will be somewhat tedious).
  • Then, modify daily work from 8 hours to 40 hours the remaining two months.

Actually, I have found a third way to do it:

  • Create five resources (Excavator 1, Excavator 2, etc).
  • Assign the five excavators to Task 1.
  • Use an assignment view ("Task Usage" or "Resource Usage").
  • Change the Excavator 3 assignment (by double-clicking its row) and set the start date of the assignment two months after the Task 1 start date (maybe you should also have to change the assignment total work hours to half its value).
  • Repeat for Excavator 4 and Excavator 5.

At the end, Excavator 1 and 2 should work the full task duration, and Excavator 3, 4, and 5 should work only during the second half of the Task.

Hope this helps. Greetings.

Your Answer

By clicking “Post Your Answer”, you agree to our terms of service, privacy policy and cookie policy

Not the answer you're looking for? Browse other questions tagged or ask your own question.