2

This is a little embarrassing, but I cannot figure out how to do this. I have added Text Style formatting, but I need to change the priority of the formatting.

I have Critical Path tasks formatted to Red, and Milestones to Blue, however, if a task is a milestone and on the critical path, I want it Red.

Is this possible? Am I missing something really obvious?

1

To answer your first question: As far as I know, there's no way to control the way conditional formatting is prioritized in MS Project.

To answer your last question: Indeed, you do miss something here. A task can't be a milestone. Well, it can be in MS Project. But in my eyes this is plain wrong. When you are using a scheduling methodology (PERT, or - like you do - CPM), a milestone is a mark to emphasize a specific point along your timeline to help you to easily see whether or not your project is on schedule.
One can argue that a milestone in fact can have some kind of "duration" (e.g. when waiting for some tests). But it definitely can't be a task. A task is an activity, a milestone is a marker.

So as MS Project handles milestones as tasks and regarding to answer one: I'd try fiddling around with the conditional formatting (first blue, then red and vice versa). That always helps with my issues.

| improve this answer | |