We run a sale of second hand goods from clients. We would set a target say 200 items this season and start contacting people we know who have items they want to sell. We would spend about 2 months doing this, then for each item we bring back to office, we need to check, research and photograph it. Then we would design and publish a sale catalogue.

How would you model this in MS-Project? Should I have a summary task that's 2 month long? But then there is no point creating 200 sub-tasks for each item. How could this be represented in MS-Project in a meaningful and useful way to track my team's progress?

1 Answer 1

1

Have a single task "Acquire 200 items" with a 2-month duration

You can have a single task named "Acquire 200 items" with a 2-month duration. If, for example, at the end of one month you have acquired only 80 items, you can show the task 40% complete.

However, if I were you. I will try to break-up that 2-month task into smaller ones. Let us say, that you estimate your team has to make about 1000 cold calls in the first 2-weeks in order to find people that have items to sell, I will track that as a separate task.

Your Answer

By clicking “Post Your Answer”, you agree to our terms of service and acknowledge you have read our privacy policy.

Not the answer you're looking for? Browse other questions tagged or ask your own question.