0

Playing around with Tempo in JIRA at the moment, how can I set the total number of hours that a resource can commit, it seems by default it sets 8 hours per resource.

Thanks

1

For general time tracking config you go to administration/issues/time tracking, there you can define amount of working hours per day and working days per week.

When you create a team in tempo, you can define the dedication or availability of each member on the team in x%

  • Yeah but it's always set to 8 hours. – bobo2000 Jan 22 '18 at 20:12
  • you have to disable time tracking first, then you can change it. Believe me, I work 7,5 hours a day :) – Homerothompson Jan 23 '18 at 12:33

Your Answer

By clicking “Post Your Answer”, you agree to our terms of service, privacy policy and cookie policy

Not the answer you're looking for? Browse other questions tagged or ask your own question.