-1

I currently have 2 identical projects beginning at different times (will be adding more).

The manager has a number of "Review" tasks spread out in the project as well as some of his own work. The Reviews take priority over his own work and I don't mind delays to his work because of this.

How can I have a resource pause their current task, carry out another task and then go back to their previous task once complete?

0
  1. Start with a well developed, logic driven schedule network.
  2. Assign the manager as a resource to the required tasks.
  3. Assign the "Review" tasks a higher priority than other competing tasks.
  4. In leveling options, select Leveling order: Priority, Standard.
  5. Check "Leveling can create splits in remaining work."
  6. Execute "Level Resource."
  7. Done.

Your Answer

By clicking “Post Your Answer”, you agree to our terms of service, privacy policy and cookie policy

Not the answer you're looking for? Browse other questions tagged or ask your own question.