When I add in the subprojects to the Master Project, the date ranges are unaffected UNTIL I expand the subproject - at which point - the dates all shift to the right. Can I prevent this?

1 Answer 1

1

No, unfortunately you can't prevent that because the data from the subprojects is only loaded when you expand them.