0

Curious if there is a way to avoid Microsoft Project auto-adjusting the assignment units, when I add a resource in the Resource name column.

In the project settings all resources are set to 100% availability and all tasks are set to fixed units.

Basically, I'd like to have a resource always enter with 100% assignment, even for tasks that are less than 8hrs, as it currently auto-adjusts the assignment based on the percentage of the workday, that the work estimate is - see below example.

I can manually adjust the assignment back to 100%, but for huge projects, this is really annoying.

Is there any way to override this?

assignment units

1 Answer 1

2

The screen shot does not show the field names, but it appears that you have a task Duration of 1 day (e.g. 8 hours), but Work set to 4 hrs (e.g. half a day). In order for resources to only work 4 hours on an 8 hour task, they must be set at 50%.

1
  • Thanks, Rachel, that is probably what happens. However, as I'm using fixed unit setting (and not fixed duration), for tasks where work units exceed 8 hours, the duration is extended, and I'd expect that for tasks shorter than, the duration should be dynamically set to less than 1 day (0,5;0,4;0,3, etc.) keeping the resource availability intact, but alas, seems like a build-in logic in Microsoft Project. Feb 16, 2018 at 11:44

Your Answer

By clicking “Post Your Answer”, you agree to our terms of service and acknowledge you have read our privacy policy.

Not the answer you're looking for? Browse other questions tagged or ask your own question.