Probably a noddy question, but need to ask. I'd like to be able to demonstrate real time slippage on my plan, for remodeling impact purposes. I have both original baseline dates and current dates added to my plan. Is there a way of linking these to show a separate column with real time, total days slippage

1

In the ribbon, open the "Baseline" drop-down menu and click on Baseline. You will be able to make visual comparisons--for each task--between the Gantt bars for the current plan versus the baseline.

0

Open up your Finish Variance column. It calculates gap between Finish Date and Baseline Finish Date.