When I try to print my Gantt schedule, it hides a bunch of my information rows. How can I fix this? See the comparison between actual Gantt and print preview below:

screenshot

1
  • 3
    What version are you using? Does this happen every time with every project? FWIW I am not able to replicate with project 2013. Jul 12, 2018 at 2:36

1 Answer 1

1

Try selecting Print Entire Project and in Page Setup select Fit to: x number of pages.

screenshot