How do I enter 'or' logic into the predecessor field? For instance, task 4 can start when task 1, 2, or 3 ends. We don't know which of 1, 2, or 3 will begin or end first.
Thank you
How do I enter 'or' logic into the predecessor field? For instance, task 4 can start when task 1, 2, or 3 ends. We don't know which of 1, 2, or 3 will begin or end first.
Thank you
You can't. "Or" relationships aren't supported in MSP (nor in any other mainstream project scheduling tool that I know of.)