I want to change the start date of a specific section in my project.
When I do that, it automatically changes the mode of this section from auto to manually schedule.
Is it possible to change the date and still remain on auto-schedule mode?
From MSP 2010, typing a date directly into the Start column of a Summary task automatically converts it to manual mode. Instead, double-click on the task and enter a "Start No Earlier Than" constraint on the Advanced tab of the Summary Task Information dialog.
You have entered information into a summary task. A summary task simply 'rolls-up' or summarises its subtasks and all date information is calculated when auto-scheduled. If you choose to over-write this calculated information, Microsoft Project will change the task mode to manual.