0

I want to change the start date of a specific section in my project.

When I do that, it automatically changes the mode of this section from auto to manually schedule.

Is it possible to change the date and still remain on auto-schedule mode?

2 Answers 2

1

From MSP 2010, typing a date directly into the Start column of a Summary task automatically converts it to manual mode. Instead, double-click on the task and enter a "Start No Earlier Than" constraint on the Advanced tab of the Summary Task Information dialog.

1
  • (Note: constraints and logic on summary tasks are generally considered bad practice. Think about adding a sectional start milestone with a SNET constraint and suitable successor relationships to the other non-summary tasks in the section.)
    – Tom Boyle
    Commented Aug 10, 2018 at 12:58
0

You have entered information into a summary task. A summary task simply 'rolls-up' or summarises its subtasks and all date information is calculated when auto-scheduled. If you choose to over-write this calculated information, Microsoft Project will change the task mode to manual.

Your Answer

By clicking “Post Your Answer”, you agree to our terms of service and acknowledge you have read our privacy policy.

Not the answer you're looking for? Browse other questions tagged or ask your own question.