-1

I am using a 5 working days & 8 hours standard calendar. My task is 30 days . I have selected a start date on Monday and end date on Friday (30th work day) but the durationn reflects as 40 days instead of 30 days? How can I ensure that the duration reflects the correct work days for the task?

  • Please provide more information such as the exact dates, list any constraints, if resources assigned, etc. Attaching a screen shot might help as well. Also, what happens if you try this same start date and duration in a new schedule with just this one task? – Rachel Hettinger Dec 10 '18 at 17:48
0

You should not be selecting start and end dates. Select the start date and duration, let project calculate the end date. Even better, don't select the start date and use predecessors to drive the date, just noting the duration.

Your Answer

By clicking "Post Your Answer", you agree to our terms of service, privacy policy and cookie policy

Not the answer you're looking for? Browse other questions tagged or ask your own question.