I am using a 5 working days & 8 hours standard calendar. My task is 30 days . I have selected a start date on Monday and end date on Friday (30th work day) but the durationn reflects as 40 days instead of 30 days? How can I ensure that the duration reflects the correct work days for the task?
-
Please provide more information such as the exact dates, list any constraints, if resources assigned, etc. Attaching a screen shot might help as well. Also, what happens if you try this same start date and duration in a new schedule with just this one task?– Rachel HettingerCommented Dec 10, 2018 at 17:48
3 Answers
Hmmm - a very quick google search gave this: https://blog.epmainc.com/more-you-want-know-about-duration-everything-you-need-know/:
When you enter a Duration value for a task in Microsoft Project, the software always calculates the schedule of the task in working days. ... For example, an elapsed Duration value of 20 days means 20 calendar days, including weekends and company holidays
So in practice, the 10 additional days are weekends.
You should not be selecting start and end dates. Select the start date and duration, let project calculate the end date. Even better, don't select the start date and use predecessors to drive the date, just noting the duration.
-
1
-
I am trying to advise best practice when scheduling. You should not be entering start date, end date and duration into Microsoft Project. Commented Mar 5, 2020 at 17:41
-
You are frame challenging the question. In pm.se, as in any other community, this needs to be done with care otherwise you'll end up attracting a lot of downvotes. Commented Jul 28, 2021 at 8:00
-
I would appreciate advise on how to respond to a such a question when somebody asks how to do something using a method that is itself causing the problems experienced. If I were working with a colleague and I saw them entering start and end dates I would explain the best practice in entering task information, and entering start and end dates is far from best practice. I have implemented Project Online with Microsoft Gold partners in large portfolios and they have all been consistent on this point. Commented Nov 4, 2021 at 8:53
-
PS - Surely the answer to the question "How can I ensure that the duration reflects the correct work days for the task" is to enter the start date and expected duration? And is pointing this out really 'frame challenging'? Commented Nov 4, 2021 at 8:57
Stop using MS Project - It is anti-Agile!
If you work for an organisation that wants to be Agile yet insists on MS Project plans, consider getting another job; trying to mix the 2 is both a waste of your time and theirs.
-
Commenting to the question is a better way of providing your view instead of writing it as an answer. Commented Nov 22, 2022 at 2:07
-
This does not provide an answer to the question. Once you have sufficient reputation you will be able to comment on any post; instead, provide answers that don't require clarification from the asker. - From Review– MCWCommented Nov 22, 2022 at 18:51