1

I find the Autosave feature to be very intrusive and it also interferes with some macros I run. I know how to disable it via File/Options/Save/untick the box, but even if I then immediately save my file the feature is re-enabled the next time I open the file, so I have to manually disable it again.

How can I either turn it off permanently (for this file only) or disable it via VBA?

Thanks

Eric

3
  • AS an FYI, whenever you save in MS Project you remove the undo history. For this reason I don't use it.
    – rapscalli
    Jan 7 '19 at 9:09
  • Agreed, that is annoying, but unfortunately I am stuck with MSP.
    – Eric
    Jan 8 '19 at 14:47
  • I should clarify, its autosave that i don't use. I too am stuck with MSP...
    – rapscalli
    Jan 14 '19 at 15:22
1

I think the problem is that my IT dept have updated my registry which I am unfortunately not able to edit. This link

https://getadmx.com/?Category=Office2016&Policy=proj16.Office.Microsoft.Policies.Windows::L_PjSaveEvery

shows what needs to be changed, and explains why it resets each time I close and reopen Project.

enter image description here