-1

This is driving me crazy!

In my 1250 line plan (MS Project 2016) with 7 resource types, I find that the results of leveling are different depending on whether I do it via "Level Resource" (with all resources selected) vs "Level All".

Given any task without resources will not be leveled (as it has no resources) why would these 2 methods give different results?

In Leveling Options I have ticked the box to "Clear Leveling values before leveling". However I have also found that despite this box being ticked I get different results if I click Level All a second time, which suggests the tick box function is not working as expected.

I need to understand this because, as you may have seen from my other posts, I am getting inconsistent results when leveling and don't know which results to trust, if any.

Your Answer

By clicking "Post Your Answer", you acknowledge that you have read our updated terms of service, privacy policy and cookie policy, and that your continued use of the website is subject to these policies.

Browse other questions tagged or ask your own question.