2

I see other people printing our project's Gantt chart with an up-to-the-date date on the bottom.

How do they to do that? Is it automatic or must one do something every time one prints the chart?

  • @tiagoperes Please stop suggesting for the ms-project tag to be added. Please read the description of the tag - it should not be combined with the ms-project-2013 tag. – Sarov Jan 8 at 20:06
  • @Sarov In this specific case the solution is not version specific. – Tiago supports GoFundMonica Jan 8 at 20:19
  • @tiagoperes If that's true then the version-specific tag should be replaced by the version-agnostic one; the Question should not contain both. – Sarov Jan 8 at 20:23
  • @Sarov that's your opinion. Already had that discussion with moderators from this community and we agreed it's acceptable with both. Not for this particular case but generally speaking. – Tiago supports GoFundMonica Jan 8 at 20:49
  • @tiagoperes Can you provide a link? – Sarov Jan 8 at 20:50
3

From here:

In the File tab, click Print, then click Page Setup.

On the Header, Footer, or Legend tab, click the Left, Center, or Right tab.

Now choose the date icon and the field will auto-fill and update when you print.

Your Answer

By clicking “Post Your Answer”, you agree to our terms of service, privacy policy and cookie policy

Not the answer you're looking for? Browse other questions tagged or ask your own question.