How can I change the working time to 2 weeks ( working - 14 days) and 1 week (not working - 7 days)? Is this able to be automatically populated?

1
  1. "Create a New Calendar" by copying the existing "Standard" (5dx8h) calendar. I would name the new calendar something like "7dx8h:2w+1w."
  2. Reset the default Work Weeks of the new calendar to include Sunday and Saturday as normal workdays.WorkWeek Mod
  3. On the Exceptions tab, add a new "Rest Week" exception. In the Details for "Rest Week", specify the exception as Nonworking, with Weekly recurrence pattern, recurring every 3 weeks on (check all 7 weekdays). Set the Range of recurrence however you need. enter image description here