Let's say I have multiple tasks that are supposed to be taken care of one after another. Each has its own date of completion.
- task 1 - will be completed on 15 march (1 day)
- task 2 - will be completed on 17 march (2 days)
- task 3 - will be completed on 18 march (1 day)
- task 4 - will be completed on 21 march (3 day)
Suddenly task 2
is delayed by two days. I would like task 3
and task 4
's dates be changed accordingly.
Right now I use teamwork. In calendar view, tasks are NOT connected to each other in any way. So if the date of one task changes, the rest stay the same. I need to manually move all tasks on the calendar.
Can such problem be taken care of in teamwork?